Postby danielgibbs » Tue Jun 16, 2015 10:28 am

Hi Dean,

Another Take off suggestion here, concrete columns are almost always measured as items (including form/reo/bracing/stripping/concrete etc etc) for example;

A 500mm x 500mm concrete column would be circa $1800m3. ATM concrete columns are being measured with the nominal concrete m3 rate (i'm using a very rough $330m3 rate for this project) which equates to a $47k gap in column budget. It's not a big issue, but it does demonstrate a level of diligence required when using takeoff.

On a positive side note, there isn't a single estimator in this office that isn't very concerned by this software :twisted:

Cheers
Attachments
rsz_concrete_columns.jpg
rsz_concrete_columns.jpg (107.13 KiB) Viewed 3502 times
danielgibbs
 
Posts: 11
Joined: Sat May 16, 2015 3:24 pm

Re: Takeoff - Concrete Columns

Postby Dean » Tue Jun 16, 2015 2:59 pm

Hi Daniel,

Good suggestion, I have added this to my suggestion list.

That is great to hear and it's only going to get better and better :)

Kind Regards
Dean
User avatar
Dean
PlusSpec Developer
 
Posts: 447
Joined: Tue Mar 18, 2014 8:25 am


Return to General Discussion and Questions

Who is online

Users browsing this forum: No registered users and 6 guests